Report For August 2018

Report Date
August 2018

Achievements this period

System build has completed for Moray House institutes and UAT testing is complete.

Issues

None

Next Steps

  • Make any amendments following UAT for Moray House Institutes
  • Continue to monitor evaluation of pilot schools 
  • Project closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
32.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
32.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
CAHSS WAM Extended Pilot
Code
HSS020
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-Sep-2017
Planning Date
08-Sep-2017
Delivery Date
10-Aug-2018
Close Date
31-Aug-2018
Overall Priority
Normal
Category
Discretionary