Report For September 2018

Report Date
September 2018

Achievements this period

Moray House remaining Institutes are now live.  Project success criteria met and the project is closed.

Issues

None

Next Steps

None

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
32.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
32.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
CAHSS WAM Extended Pilot
Code
HSS020
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-Sep-2017
Planning Date
08-Sep-2017
Delivery Date
10-Aug-2018
Close Date
31-Aug-2018
Overall Priority
Normal
Category
Discretionary

Documentation