Student Voice - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
March 2019 BLUE 31.0 days 34.6 days 0.4
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 14 May 2018
Planning Date
Friday, 6 July 2018
Delivery Date
Thursday, 14 February 2019
Close Date
Friday, 29 March 2019
Project information
Project Code
HSS023
Programme
CAHSS Portfolio Projects
Session
18/19
17/18
Organisational Unit
College of Humanities & Social Science
Project Management Office (if relevant)
ISG PMO
Project Category
Discretionary
Project Classification
Run
Funding Source
Sponsor Funded
Overall Priority
Normal