Report for May 2018

Report Date
May 2018

Achievements

  • Project Initiated

Issues

  • None

Next Steps

  • Project planning completed
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
25.0 days
Activity this month
2.5 days
Activity this year
2.8 days
Activity to date
2.8 days
Estimate to complete current year
17.2 days
Estimate to complete future years
5.0 days

Project Info

Project
Student Voice
Code
HSS023
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
14-May-2018
Planning Date
06-Jul-2018
Delivery Date
14-Feb-2019
Close Date
29-Mar-2019
Overall Priority
Normal
Category
Discretionary