Report for February 2019

Report Date
February 2019

Report for February 2019 by Ken Miller

Achievements

  • Complete options paper for review meeting.
  • Options Paper review meeting.
  • Complete "Outcomes Report" summarising Options Paper review meeting.

Issues

Next Steps

  • Project Closure.

Milestones

Stage Milestone Due Date Complete
Analyse

Requirements sign off

10-Oct-2018  Yes
Analyse    Analysis Phase Complete 16-Nov-2018  Yes
Deliver Options Paper Signed Off and Deliver Phase Completed   14-Feb-2019  Yes
Build Project Closure 28-Feb-2019  No

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
RAG Commentary
Project in step with project plan.
Change Status
Time
No Change
Cost
Moderate
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Project sponsor aware of minor overrun.
Change Commentary
Project sponsor requested final summary report causing minor overrun.
Activity
Approved budget
31.0 days
Activity this month
1.5 days
Activity this year
21.8 days
Activity to date
34.0 days
Estimate to complete current year
0.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Voice
Code
HSS023
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
14-May-2018
Planning Date
06-Jul-2018
Delivery Date
14-Feb-2019
Close Date
29-Mar-2019
Overall Priority
Normal
Category
Discretionary