Report for March 2019

Report Date
March 2019

Report for March 2019 by Ken Miller

Achievements

  • Complete Project Closure Report
  • Formal closure approved on 29/3/2019.
  • Project Closed

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
BLUE
RAG Commentary
Project in step with project plan.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
31.0 days
Activity this month
0.6 days
Activity this year
22.3 days
Activity to date
34.6 days
Estimate to complete current year
0.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Voice
Code
HSS023
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
14-May-2018
Planning Date
06-Jul-2018
Delivery Date
14-Feb-2019
Close Date
29-Mar-2019
Overall Priority
Normal
Category
Discretionary