Report for June 2018

Report Date
June 2018

Achievements

  • Project planning is underway
  • Project brief has been drafted and signed of by key stakeholders

Issues

  • PM contract ends on 13th July and a replacement PM is still to be identified

Next Steps

  • Project planning to be signed off by WIS
  • As-is processes to be drafted and signed off
  • Draft requirements produced
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project green as baseline project plan and costs have yet to be approved.
Change Status
Activity
Approved budget
25.0 days
Activity this month
6.4 days
Activity this year
9.3 days
Activity to date
9.2 days
Estimate to complete current year
9.5 days
Estimate to complete future years
9.3 days

Project Info

Project
Student Voice
Code
HSS023
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
14-May-2018
Planning Date
06-Jul-2018
Delivery Date
14-Feb-2019
Close Date
29-Mar-2019
Overall Priority
Normal
Category
Discretionary