Report for August 2018

Report Date
August 2018

Achievements

  • Student intern completed initial BRD document

Issues

  • Change of PM - PM left university on 13 July, new PM is started on 15 August. Handover occurred with the student intern who provided cover for the PM.

Next Steps

  • BRD document released for review
  • Sign off As-is and BDR document
  • Investigation of proposed options against requirements

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Timeline to be revised to suit availability of business partner, project closure expected to move from 5/10/2018 to 29/11/2018.
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
Timeline to be revised to suit availability of business partner, project closure expected to move from 5/10/2018 to 29/11/2018. Awaiting confirmation.
Activity
Approved budget
31.0 days
Activity this month
3.8 days
Activity this year
3.8 days
Activity to date
16.1 days
Estimate to complete current year
17.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Voice
Code
HSS023
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
14-May-2018
Planning Date
06-Jul-2018
Delivery Date
14-Feb-2019
Close Date
29-Mar-2019
Overall Priority
Normal
Category
Discretionary