Report for November 2018

Report Date
November 2018

Report for November 2018 by Ken Miller

Achievements

  • Achieve BDR sign off for version 1.2 of the BRD
  • Investigation of proposed in house options against requirements, responses received.

Issues

  • Unitu demonstration schedule for 5/12/2018 this will delay production of Options Paper.

Next Steps

  • Draft options paper covering the suitability of Learn, Unitu and Microsoft Teams to address the requirements held in BRD v1.2 for review.
  • Feedback to be incorporated and final options paper and signed off.

Milestones

Stage Milestone Due Date
Analyse

Requirements sign off

02-Nov-2018
Analyse    Analysis Phase Complete 16-Nov-2018
Deliver Options Paper Signed Off   30-Nov-2018
Build Project Closure 14-Dec-2018

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Timeline revised to allow for demonstration of external Unitu product. The delay has been raised with the Sponsor and the Business.
Change Status
Time
Moderate
Cost
Within Tolerance
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
Yes
Escalated to
This has been raised this with the Project Sponsor and Programme Manager
Change Commentary
Timeline revised to allow for demonstration of external Unitu product. This will cause a slight delay in the production of the options paper.
Activity
Approved budget
31.0 days
Activity this month
2.7 days
Activity this year
16.5 days
Activity to date
28.8 days
Estimate to complete current year
5.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Voice
Code
HSS023
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
14-May-2018
Planning Date
06-Jul-2018
Delivery Date
14-Feb-2019
Close Date
29-Mar-2019
Overall Priority
Normal
Category
Discretionary