Report for January 2019

Report Date
January 2019

Report for January 2019 by Ken Miller

Achievements

  • Complete initial draft options paper for review.
  • Feedback to be incorporated and final options paper forwarded to review meeting attendees.
  • PICCL raised for revised Options Paper review meeting and project closure

Issues

Next Steps

  • Options Paper review meeting.
  • Project Closure.

Milestones

Stage Milestone Due Date
Analyse

Requirements sign off

10-Oct-2018
Analyse    Analysis Phase Complete 16-Nov-2018
Deliver Options Paper Signed Off and Deliver Phase Completed   14-Feb-2019
Build Project Closure 28-Feb-2019

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Timeline revised to allow for demonstration of external Unitu product to feed into Options Report review meeting and project closure.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
This has been raised this with the Project Sponsor and Programme Manager
Change Commentary
Timeline revised for options paper review and project closure.
Activity
Approved budget
31.0 days
Activity this month
1.2 days
Activity this year
20.3 days
Activity to date
32.6 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Student Voice
Code
HSS023
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
14-May-2018
Planning Date
06-Jul-2018
Delivery Date
14-Feb-2019
Close Date
29-Mar-2019
Overall Priority
Normal
Category
Discretionary