Report for February 2019

Report Date
February 2019

Achievements in the Last Period

  • The issue that led to the failed SSO authentication was investigated and understood
  • Milestones were updated
  • The TAD was completed and passed to Production (DEV environment and EASE Authentication)
  • Script changes were made and EASE authentication (SSO) was applied to Xerte - TEST
  • TEST Xerte with EASE authentication was signed off on TEST
  • Script changes were rolled out / deployed to LIVE - Tuesday 26-Feb-2019
  • A draft Project Closure Report has been prepared 

 

Issues

  • Issue #11:  Additional Budget After EASE Authentication Investigation / Fix Put in Place  - EASE authentication has proved more challenging / longer to code / implement than expected.  Applying authentication has cost an additional 14 days of effort, including a failed deployment attempt, an investigation into the failed EASE Deployment / applying the subsequent code fix and then a final successful deployment to LIVE.  The project is AMBER as a result.

 

Next Steps

  • Finalise / agree the Operational Level Agreement (OLA)
  • Get the TAD signed off by Production
  • Review / finalise the Closure Report
  • Close the Project 

 

Milestones

Agreed at WIS Friday, 22 February 2019:

11-Jan-2019 Sign Off EASE Authentication - TEST
26-Feb-2019 Deploy EASE Authentication to LIVE
06-Mar-2019 Sign Off EASE Authentication - LIVE
08-Mar-2019 Closure

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
ISSUE: EASE authentication has proved more challenging / longer to code / implement than expected. Applying authentication has cost an additional 14 days of effort, including a failed deployment attempt, an investigation into the failed EASE Deployment / applying the subsequent code fix and then a final successful deployment to LIVE. The project is AMBER as a result.
Change Status
Time
Within Tolerance
Cost
Moderate
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
ISSUE: EASE authentication has proved more challenging / longer to code / implement than expected. Applying authentication has cost an additional 14 days of effort, including a failed deployment attempt, an investigation into the failed EASE Deployment / applying the subsequent code fix and then a final successful deployment to LIVE. The project is AMBER as a result.
Activity
Approved budget
46.0 days
Activity this month
5.1 days
Activity this year
41.8 days
Activity to date
59.2 days
Estimate to complete current year
0.7 days
Estimate to complete future years
0.0 days

Project Info

Project
Support for the Xerte Pilot
Code
HSS024
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
04-Jun-2018
Planning Date
22-Jun-2018
Delivery Date
26-Feb-2019
Close Date
22-Mar-2019
Programme Priority
4
Overall Priority
Normal
Category
Discretionary