w/c 21st September 2020
  • Remaining Outstanding Tasks 
    • The supplier has advised that the work on the CR request has now commenced - one week earlier than scheduled
  • OLA
    • Discussions to finalise the OLA on-going
Andrew Stewart 23-Sep-2020
w/c 7th September 2020
  • Remaining Outstanding Tasks 
    • The supplier has advised that the work can commence w/c 29th of September with a completion date on or before the 13th October. However, this is dependant on UoE sign-off of CR request  
Andrew Stewart 23-Sep-2020
w/c 24th August 2020
  • Project meeting held to review current status regarding remaining post go-live issues 
    • currently awaiting schedule from supplier to develop and implement changes 
    • issue with appointment sessions resolved 
    • system operational and in use 
Andrew Stewart 25-Aug-2020
w/c 18th May 2020
  • Go-live Planning 
    • Confirmation received from IS Apps Production for go-live
    • Dates for go-live confirmed for Wednesday 27th May 
    • Further user training slots confirmed 
      • Admin (0.5 day) - Wednesday 3rd June
      • SuiteCRM - (0.5 day) - Thursday 4th June 
    • Conference call held to clarify aspects regarding the go-live and subsequent training 
Andrew Stewart 22-May-2020
w/c 4th May 2020
  • Database Migration 
    • Continued to investigate missing 2020 data 
    • Individual analysis of individual tables highlighted a discrepancy with the number of records in teh Counselling Session table between UoE and SalesAgility.  It would appear that approximately 500 records had been dropped.  
    • Database subsequently re-sent via SFTP and confirmation that table rows matched
Andrew Stewart 22-May-2020
w/c 27th April 2020
  • Database Migration 
    • UAT is on-going with issues noted regarding missing consultations
    • Noted that 2020 data is not present
    • Review of source data confirmed 2020 data present
    • Discovered that the supplier development team had used the wrong data file in error
    • 2020 data has now been loaded.  However not all 2020 data appears to be present
  • Single Sign On 
    • on going testing with Live environment 
Andrew Stewart 22-May-2020
w/c 20th April 2020
  • SSO
    • Project Manager still experiencing difficulties in accessing live site after successfully authenticating 
    • Additional accounts created on the live site for the business lead and technical lead to assist with testing 
  • Database migration
    • The issue has been resolved that was preventing access to the test site and so testing can now continue
Andrew Stewart 21-Apr-2020
w/c 13th April 2020
  • SSO
    • Still unable to access the site after SSO supplier updates 
  • Database Migration 
    • The 2020 data has been loaded and available for review
    • Call scheduled for Wednesday 15th April to discuss database migration questions
Andrew Stewart 15-Apr-2020
w/c 6th April 2020
  • SSO
    • user account details reset for further testing 
    • SSO being updated by the supplier 
  • Database Migration 
    • UAT is underway with positive results to date
    • Currently awaiting the 2020 data to be loaded - only 2019 data loaded so far
Andrew Stewart 15-Apr-2020
w/c 30th March 2020
  • Database conversion
    • SalesAgility have advised that the new database conversion has been completed and is ready to test in the secure UAT environments.  Along with teh conversion comes a number of factors that require further consideration by HopePark.   The business lead will now commence UAT and commence review.  Meeting scheduled for Monday 6th April to review progress
  • Live Environment 
    • This is now available 
  • SSO
    • DNS settings updated within UoE
Andrew Stewart 02-Apr-2020
w/c 23rd March 2020
  • Go-Live preparations
    • Data from the live MS Access database has been extracted, and transferred to the supplier on 24/03/20
  • SSO
    • Call raised to update DNS 
Andrew Stewart 23-Mar-2020
w/c 16th March 2020
  • User Training
    • Due to the current circumstances re coronavirus planning, it has been decided to re-schedule this training to a later date
  • Outstanding Issues
    • JIRA HSS027-58 closed 
  • Technical resourcing
    • Dev Tech resource assigned to assist with scheduled go-live w/c 13/04/20
  • Strategy going forward
    Andrew Stewart 23-Mar-2020
    w/c 9th March 2020 Andrew Stewart 23-Mar-2020
    w/c 2nd March 2020 Andrew Stewart 23-Mar-2020
    w/c 24th February 2020 Andrew Stewart 23-Mar-2020
    w/c 17th February 2020 Andrew Stewart 23-Mar-2020
    w/c 10th February 2020 Andrew Stewart 23-Mar-2020
    w/c 3rd February 2020 Andrew Stewart 23-Mar-2020
    w/c 27th January 2020 Andrew Stewart 23-Mar-2020
    w/c 20th January 2020
    • Go-Live Preparations
      • GoCab paperwork submitted for go-live on 5th February
      • Request to Applications Management to commence Deployment CheckList 
      • Request for Technology Management  resource to complete Deployment CheckList 
    • piccl submitted to WIS re revised dates and budget 
    • User Acceptance Testing 
      • UAT Status schedule prepared 
      • UAT commencing 
      • Review of outstanding JIRAs undertaken with the business and the suppler
    • Risk Log updated
    • SSO
      Andrew Stewart 21-Jan-2020

      Project Info

      Project
      Hope Park Counselling Centre System Implementation
      Code
      HSS027
      Programme
      CAHSS Portfolio Projects
      Management Office
      ISG PMO
      Project Manager
      Andrew Stewart
      Project Sponsor
      Fraser Muir
      Current Stage
      Close
      Status
      Closed
      Project Classification
      Run
      Start Date
      24-Aug-2018
      Planning Date
      29-Aug-2018
      Delivery Date
      27-May-2020
      Close Date
      06-Nov-2020
      Overall Priority
      Normal
      Category
      Discretionary

      Documentation