Project Brief

Document Sign Off

Name Project Role Date Signed Off
Fraser Muir Project Sponsor 07/03/2019
Leon Toland Project Manager 05/03/2019
Alistair Duthie Business Lead / Senior User 06/03/2019
Iain Fiddes Senior Supplier 11/03/2019
Bill Lee  Software Dev Lead 06/03/2019
Suran Perera IS Production – App Services Group (AHSS & USG) 04/03/2019
Brandi Headon Student Systems Operations 04/03/2019
Muriel Mewissen Programme Manager - CAHSS 07/03/2019

Version Control

Date Version Author Section/s Amendment/s
08/02/2019 0.1 Leon Toland All Draft
18/02/2019 0.2 Leon Toland All Revisions to reflect Senior User and Sponsor comments
25/02/2019 0.3 Leon Toland 4, 5, 6, 9, 12, 15 Further revisions to reflect additional clarification of delivery impact associated with EUCLID data feed changes to SPQS
01/03/2019 0.4 Leon Toland 4, 6, 7, 9, 10, 12, 15 Further Planning phase revisions to reflect project stakeholder feedback at HSS029 Kick-off meeting on March 1st.
04/03/2019 0.5 Leon Toland 2, 4, 6, 7, 9, 10, 12, 14, 15

Final revisions prior to stakeholder approval, to reflect:

  • Reversion to the original single delivery phase approach following Senior User review with SSP Operations, and
  • Updated Software Dev team resourcing forecasts.

Project Info

Project
School Programme Quality System (SPQS) Improvements
Code
HSS029
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-Feb-2019
Planning Date
27-Feb-2019
Delivery Date
11-Dec-2019
Close Date
21-Feb-2020
Programme Priority
8
Overall Priority
Higher
Category
Discretionary