w/c 30th September 2019 |
- Project Funding
- The Programme Manager advised that the funding for the Phase 2 development had been approved and it would be funded from the College Ring Fenced Budget
- Project Governance
- The project website was updated to incorporate the plan and estimate for Phase 2
- Risk log reviewed and updated, including new Risk 12 being added
- Project milestone and budget changes submitted to WIS for 11th October
- Project meeting scheduled for Tuesday 8th October to rank Phase 2 developments
|
Andrew Stewart |
01-Oct-2019 |
w/c 23rd September 2019 |
|
Andrew Stewart |
01-Oct-2019 |
w/c 16th September 2019 |
- Phase 2 Development
- the outcome of the meeting held on 18th September to review the phase 2 proposal
- project plan and timelines approved - to commence w/c 14th October
- required activity prioritised
- project communications discussed and agreed - daily conference calls to review progress
|
Andrew Stewart |
01-Oct-2019 |
w/c 9th September 2019 |
- Phase 2 Development
- meeting scheduled for 18th September to review project proposal
|
Andrew Stewart |
01-Oct-2019 |
w/c 8th July 2019 |
- Project escalation
- to try and secure development resource to deal with any snagging issues w/c 15th July
- Approval from Head of Project services to increase project priority to 'Higher'
- Resource conflict raised with DTI028 for developer resource (project manager advised)
- created new risk - Risk 11 - No benefits delivered in 2018-19
- Two new Test EASE accounts created to assist with testing
|
Andrew Stewart |
11-Jul-2019 |