Report for January 2020

Report Date
January 2020

Achievements in Last Period:

  • None.

Issues:

  • Agreement on the content of the OLA needs to be concluded. Presently with the Computing Officer for Operational Services.

Next Steps:

  • Project closure.
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
OLA sign-off is the sole remaining task being brought to conclusion by the Computing Officer of Operational Services. Earlier guidance was that this is imminent with closure expected within the next few days.
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Slight overrun with budget and project completion.
Activity
Approved budget
95.0 days
Activity this month
1.5 days
Activity this year
40.5 days
Activity to date
97.5 days
Estimate to complete current year
0.5 days
Estimate to complete future years
0.0 days

Project Info

Project
School Programme Quality System (SPQS) Improvements
Code
HSS029
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-Feb-2019
Planning Date
27-Feb-2019
Delivery Date
11-Dec-2019
Close Date
21-Feb-2020
Programme Priority
8
Overall Priority
Higher
Category
Discretionary