Project Status Reports

Title Report Date Time Cost Scope Overall Change
August 2020 Monthly Project Report August 2020 BLUE BLUE BLUE BLUE No Change
July 2020 Monthly Progress Report July 2020 GREEN GREEN GREEN GREEN No Change
Report for June 2020 June 2020 GREEN GREEN GREEN GREEN No Change
Report for March 2020 March 2020 BLUE Significant
February 2020 Monthly Project Report February 2020 GREEN GREEN GREEN GREEN
Monthly Project Report for January 2020 January 2020 AMBER AMBER AMBER AMBER No Change
Report for December 2019 December 2019 GREEN AMBER GREEN AMBER No Change
Monthly Project Report November 2019 GREEN GREEN GREEN GREEN No Change
Monthly Project Report October 2019 AMBER AMBER GREEN AMBER Significant
Monthly Project Report September 2019 GREEN AMBER GREEN AMBER No Change
Report for August 2019 August 2019 GREEN GREEN GREEN GREEN No Change
Report for July 2019 July 2019 GREEN GREEN GREEN GREEN No Change
Monthly Project Report June 2019 GREEN GREEN GREEN GREEN No Change

Project Info

Project
Student Voice Platforms Pilot
Code
HSS030
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
05-Jun-2019
Planning Date
22-Jul-2019
Delivery Date
12-Aug-2020
Close Date
14-Aug-2020
Overall Priority
Normal
Category
Discretionary