Report for June 2020
- Report Date
- June 2020
Achievements
- Project team was taken out of suspension in mid June.
- Meeting took place 18-Jun and decided to progress and decide action in mid July when information should be available, or with as much information as has been collected
- 615 responses to survey at this time
- Sponsor and Student's association felt the Pilot has achieved it's purpose but now with a new way of working we will move forward on 2020/21
- Student's Association feels will hugely benefit from the programme list of enrolled student’s information and look forward to working with this next year
Issues
- No new issue
Next Steps
- Amend milestones
- Meeting to be held on 15-July to discuss the results and review feedback obtained to date
- Discuss thoughts on hybrid working and student choices and how this will work in practice
- Reflections from pilot
- Benefits from pilot
- Closure and close project
Milestones
Milestones | Date |
Deliver Report recommendations | 27-Jul-2020 |
Sign off Report recommendations (Major) | 29-Jul-2020 |
Closure of Project (Major) | 31-Jul-2020 |
- Approved budget
- 30.0 days
- Activity this month
- 1.0 day
- Activity this year
- 18.0 days
- Activity to date
- 29.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days