July 2020 Monthly Progress Report

Report Date
July 2020

Achievements

  • Amended milestones
  • Meeting held on 15-July to discuss the results and review feedback obtained to date
  • Discussed initial thoughts on hybrid working and student choices and how this will work in practice 
  • Draft recommendations from pilot
  • Draft Closure and prepared to close project

Issues

  • No new issues

Next Steps

  • Sign off report recommendations from pilot
  • Draft Closure and prepared to close project
  • Closure and close project

Milestones

Milestones Date
Deliver Report recommendations 10-Aug-2020
Sign off Report recommendations (Major) 12-Aug-2020
Closure of Project (Major) 14-Aug-2020
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
30.0 days
Activity this month
2.0 days
Activity this year
20.0 days
Activity to date
31.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
1.0 day

Project Info

Project
Student Voice Platforms Pilot
Code
HSS030
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
05-Jun-2019
Planning Date
22-Jul-2019
Delivery Date
12-Aug-2020
Close Date
14-Aug-2020
Overall Priority
Normal
Category
Discretionary