August 2020 Monthly Project Report

Report Date
August 2020

Achievements

  • Signed off report recommendations from pilot
  • Draft Closure and circulated closure report
  • Closure and closed project

Issues

  • No new issues

Next Steps

  • No next steps

Milestones

  • No more milestones

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
31.0 days
Activity this month
1.5 days
Activity this year
1.5 days
Activity to date
32.5 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Voice Platforms Pilot
Code
HSS030
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
05-Jun-2019
Planning Date
22-Jul-2019
Delivery Date
12-Aug-2020
Close Date
14-Aug-2020
Overall Priority
Normal
Category
Discretionary