Organisation
Work/Task Breakdown
*Days are worst case scenario
O1 To update to the latest version of Xerte
|
Tasks |
Who |
P |
Days* |
When |
O1 D1 |
Upgrade Xerte from v3.6 to v3.8 on
incs peer testing & documentation |
Software Dev
|
M |
6d |
9 Mar to 3 Apr 20 |
+ peer testing & documentation |
Alison for UAT Software Dev |
6-10 Apr 20
8-13 Apr 20 |
|||
Upgrade Xerte from v3.6 to v3.8 on
|
Software Dev
|
20 Apr 20 to 22 Apr 20 |
|||
|
Alison & Karen Software Dev |
M |
2d |
24 - 30 Apr 20
24 - 30 Apr 20
|
O2 To allow automatic creation of new accounts
|
Tasks |
Who |
P |
Days |
When |
O2 D1 |
|
DevTech & Alison |
M |
2d |
9 Mar to 29 Apr 20 |
O2 D1 |
|
DevTech Software Dev
|
M |
3d 3d |
6 Apr to 29 Apr 20 |
O2 D1 |
|
O3 Allow external access to Xerte learning objects
|
Tasks |
Who |
P |
Days |
When |
O3 D1 |
About making sure that if a learning object is public the private learnings objects cannot be accessed in any way |
Software Dev |
M |
2d |
10 Mar to 17 Apr 20
|
O3 D2 |
|
Software Dev
|
M |
4d |
23 Apr to 15 May 20 |
O3 D2 |
|
Software Dev |
O4 Review and update supporting documentation
- Don’t create new policies if already exist
|
Tasks |
Who |
P |
Days |
When |
O4 D1 |
|
Alison |
|
|
To 28 May 20 |
O4 D2 |
|
Alison |
|
|
To 28 May 20 |
O4D3 |
|
Karen |
|
|
To 28 May 20 |
O4 D4 |
|
Alison |
|
|
To 28 May 20 |
O4 D5 |
|
Karen |
|
|
To 28 May 20 |
O5 To contribute to a business case to be submitted to LTW for Xerte to become a centrally supported service
|
Tasks |
Who |
P |
Days |
When |
O5 D1 |
|
Muriel, Sue, Alison |
3d Inc in PM
|
|
To 5 Jun 20 |
O5 D1 |
|
Karen Alison
|
|
|
|
O5 D2 |
|
Karen plus All |
|
|
To 5 Jun 20 |
O5 D3 |
|
Alison Karen Software Dev
|
|
0.5d |
To 5 Jun 20 |
Resources, Skills and Costs
Task |
Effort |
|
|
5 |
2d plus time for business case 3d |
|
10 |
20 weeks at 0.5d per week = 10d Includes work on business case |
|
none |
|
|
3 |
|
|
2 |
|
|
2.5 |
|
|
1.5 |
|
|
1 |
|
|
1 |
|
|
1 |
|
|
21 |
|
|
5 |
|
Total IS-Apps |
54d |
Worst case scenario |
Total LTW Services |
|
|
Total Service Owner |
|
|
Overall Total |
|
|
Project Stakeholders
Name | Business Area | Role | Communication Plan |
---|---|---|---|
Adrian Richardson | Software Development | Software Development Lead |
Project team member |
Alison Christie | University Business School- Xerte Service Owner | Business Lead & Senior User |
Project Team Member Xerte Subject Matter Expert |
Fraser Muir | CAHSS - Portfolio Owner | Project Sponsor | |
Karen Howie | LTW | DLAM Team Manager |
Project team member |
Muriel Mewissen | IS ProjectServices | Portfolio manager | |
Nik Pardoe | Development Technology | Xerte System Administrator |
Project team member |
Peter Jackson | Development Technology | Xerte System Administrator |
Project team member |
Sheila Fraser | Head of IT for the College of Medicine and Veterinary Medicine | MVM rep | |
Sue Woodger | IS Project Services | Project Manager |
Project team member |
Suran Perera | Production Management | Application Development Team Manager (CAHSS) |
Project team member |
Victoria Dishon | Head of IT for the College of Science and Engineering | CSE rep |
Project Estimations
Link to Estimation Log
Training
- Currently no-one can get access to Xerte without training, Alison Christie runs the training
- A Xerte User Guide and Xerte support videos have been created for staff and students.