Impact
Priority and Funding
This project's priority is Normal.
This project funding is 40 days comprised from:
- 20 days CAHSS's CORE Ring-Fenced budget
- 20 days from Service Management's RDS budget ITSR20-3.2 (Service management RDS/Account management/Visitor Registration)
Please note that this 40 days budget and funding will only cover the project to the end of Systems Analysis and Design. Further budget will be required for Implementation.
Impact and Dependencies
No direct dependencies but there are several other projects active that are related to this project:
LIB002: Is looking at improving the VRS load to the library system Alma
HSS033: Is completing a Business Process and Systems Review for COL
All PMs and BAs on this project and on LIB002 and HSS033 are aware of the work ongoing and have agreed to keep each other informed of any cross-over relevance.
There is an ITI project - ENT212 - which is looking at Multi-factor authentication and conditional access. The PMs will maintain awareness of expected delivery from ENT212 and HSS034 to ensure any impact is understood.
In addition, the People and Money programme is also looking at how to issue credentials to people before they are members of staff (IE at the point of a contract being offered but before accepting the offer). This is similar to Objective 4 in this project.
Project Risks
Please note that this project, like all projects, is subject to risk due to Covid-19. The Covid-19 risk is held at portfolio level.
Ref | Title | Initial Risk | Current Risk | Management Approach | Risk Owner |
---|---|---|---|---|---|
1 | IS Applications Dev Services staff availability | AMBER | AMBER | Reduce | Paul Mcnulty |
2 | IS Applications Production management availability | GREEN | GREEN | Reduce | Ana Heyn |
3 | IS Apps Service Management availability | GREEN | GREEN | Reduce | Alex Carter |
4 | IS Apps PM and BA availability | AMBER | AMBER | Reduce | Muriel Mewissen |
5 | Lack of availability of College Staff for Requirements consultation and UAT | GREEN | GREEN | Reduce | Fraser Muir |
6 | Insufficient budget | AMBER | AMBER | Reduce | Fraser Muir |
7 | Industrial action in 2020 | AMBER | AMBER | Retain | Fraser Muir |
8 | Risk of scope creep due to challenges of current VRS system | AMBER | AMBER | Reduce | Fraser Muir |
9 | Risk of scope creep and/or delay due to identity management and service provisioning considerations in the Core Systems Programme | GREEN | GREEN | Reduce | Dave Berry |
10 | Delay in delivery | AMBER | AMBER | Reduce | Susan Ridder-Patrick |