Report for March 2020

Report Date
March 2020

Achievements this period

  • Project brief re-drafted
  • Estimation completed

Issues

  • Planning milestone requiring revisions for a second time as sponsor and Head of Service management have not approved the Brief

Next Steps

Project Brief to be approved or the project to be considered for withdrawal. 

Milestones

To be approved as part of Brief

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
20.0 days
Activity this month
9.1 days
Activity this year
16.1 days
Activity to date
16.1 days
Estimate to complete current year
3.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Visitor Registration System (VRS) bulk upload and creation
Code
HSS034
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Fraser Muir
Current Stage
Close
Status
Withdrawn
Project Classification
Grow
Start Date
07-Feb-2020
Planning Date
24-Apr-2020
Delivery Date
09-Oct-2020
Close Date
29-May-2020
Overall Priority
Normal
Category
Discretionary

Documentation