Impact
Priority and Funding
Normal. Sponsor-funded.
Impact and Dependencies
Dependent upon data entry by Business before new data release by end of March.
Impact from EPCC TBC mid-Feb.
Lessons learned from previous projects
N/A
Project Risks
Ref | Title | Initial risk | Current risk | Status | Approach | Owner |
---|---|---|---|---|---|---|
1 | Strikes | RED | GREEN | Open | Reduce | Christine Bell |
2 | Short time-frame for delivery with limited resource | RED | AMBER | Open | Retain | Christine Bell |
3 | Improvement approval workflow delays | AMBER | GREEN | Open | Reduce | John Allison |