Report for September 2024 - DRAFT

Report Date
September 2024

Achievements this period

  • Fortnightly team meetings continuing
  • Closure report shared with outgoing Programme Manager, Senior Supplier and Project Sponsor
  • Budget confirmed for next project with budget holder
  • Developer has now left the University of Edinburgh, this project will close with a new project to start.

Issues

  • The Project is extended to complete this phase of work. The milestones and budget need to be confirmed.
  • Production resource is limited. Releases will need to planned around this - John Allison taking up with Production
  • Budget was confirmed to the end of March - needs to be adjusted taking the extension into account

Next steps

  • Close Project, start new Project for 24/25
  • Update documentation for handover
  • Ongoing Amnesties DB work
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Moderate
Cost
Moderate
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
16.4 days
Activity this year
37.8 days
Activity to date
440.0 days
Estimate to complete current year
0.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Peace Agreements Database - Continuous Improvements 22/23
Code
HSS042
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Alan Donald
Project Sponsor
Christine Bell
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
16-Jan-2023
Planning Date
15-Feb-2023
Delivery Date
20-May-2024
Close Date
04-Dec-2024
Programme Priority
4
Overall Priority
Higher
Category
Discretionary