Report for October 2024 - DRAFT

Report Date
October 2024

DRAFT

Achievements this period

  • New project started
  • Closure report shared with outgoing Programme Manager, Senior Supplier and Project Sponsor
  • Budget confirmed for next project with budget holder
  •  

Issues

  • The Project is extended to complete this phase of work. The milestones and budget need to be confirmed.
  •  

Next steps

  • Close Project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Moderate
Cost
Moderate
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Activity
Activity this month
4.3 days
Activity this year
42.5 days
Activity to date
444.8 days
Estimate to complete current year
0.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Peace Agreements Database - Continuous Improvements 22/23
Code
HSS042
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Alan Donald
Project Sponsor
Christine Bell
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
16-Jan-2023
Planning Date
15-Feb-2023
Delivery Date
20-May-2024
Close Date
04-Dec-2024
Programme Priority
4
Overall Priority
Higher
Category
Discretionary