Report for October 2023
- Report Date
- October 2023
Achievements this period
- Project Brief approved at Apps Review
- Training has commenced with Exec Ed Team training completed and training scheduled for Events Team and main Business School users
- Licences have been migrated from Business School Salesforce Org to IRM for Exec Ed Team with remaining licences agreed with Salesforce to transfer in December
- Sandbox environment has been set up
- Connector from Business School Salesforce Org to IRM has been set up
- Migration plan has been reviewed with two of the Senior Users
Issues
- Migration Plan and Business Sign off is awaiting confirmation from one of the Senior Users who was on annual leave. This has resulted in extending some of the milestones which has been approved by the Project Sponsor and Project Team. The migration is currently on target for December
Next Steps
- Finalise business requirements with remaining Senior User
- Finalise migration plan
- Migrate data to Sandbox for UAT and sign off
- Complete User Training
- Approved budget
- 20.0 days
- Activity this month
- 7.5 days
- Activity this year
- 7.5 days
- Activity to date
- 7.5 days
- Estimate to complete current year
- 12.5 days
- Estimate to complete future years
- 0.0 days