Report for August 2024
- Report Date
- August 2024
Achievements this period
- Awaiting final sign off of project brief – will be submitted to Apps Review by 6 Sept 24
- Supplier agreed to work and timescales
Issues
- No issues this month
Next Steps
- Meeting to discuss design and build with Production, DevTech and Supplier
- Work to begin on building new servers
Commentary: Project is. Green
Milestones
Milestone |
Due Date |
Project Brief |
30 Aug 2024 |
Creation of TEST and LIVE Rocky servers |
6 Sep 2024 |
TEST environment OCS upgrade completed |
30 Sep 2024 |
LIVE environment OCS upgrade completed |
14 Oct 2024 |
Post deployment support |
25 Oct 2024 |
Close |
31 Oct 2024 |
These are project brief milestones - still to be approved by AppsReview
- Approved budget
- 10.0 days
- Activity this month
- 4.0 days
- Activity this year
- 9.0 days
- Activity to date
- 9.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days