Report for August 2024

Report Date
August 2024

Achievements this period

  • Awaiting final sign off of project brief – will be submitted to Apps Review by 6 Sept 24
  • Supplier agreed to work and timescales

Issues

  • No issues this month

Next Steps

  • Meeting to discuss design and build with Production, DevTech and Supplier
  • Work to begin on building new servers

 

Commentary:  Project is. Green

 

Milestones

Milestone

Due Date

Project Brief

30 Aug 2024

Creation of TEST and LIVE Rocky servers

6 Sep 2024

TEST environment OCS upgrade completed

30 Sep 2024

LIVE environment OCS upgrade completed

14 Oct 2024

Post deployment support

25 Oct 2024

Close

31 Oct 2024

These are project brief milestones - still to be approved by AppsReview

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
10.0 days
Activity this month
4.0 days
Activity this year
9.0 days
Activity to date
9.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
OCS Upgrade
Code
HSS046
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Euan Cameron
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
01-Jun-2024
Planning Date
04-Sep-2024
Delivery Date
14-Jan-2025
Close Date
31-Jan-2025
Programme Priority
4
Overall Priority
Normal
Category
Discretionary