Report for September 2024
- Report Date
- September 2024
Achievements this period
- Project brief approved 4 Sep 24
Issues
While PM was on annual leave 3 tasks were to be completed
- Meeting arranged for 13 Sep to agree server design and agent service names (Supplier, Production and Dev Services)
- Supplier and Production to have agreed Vendor access method
- Servers ordered and initial work begun
The meeting of 13 Sept did not happen as the Supplier could not make it. We therefore still have to agree the server design, agent names and vendor access. The supplier has been asked to supply dates as to when they can attend a meeting and we will work round those dates.
However, the completion date for the Test server is 30 September 24 and this will not be met. New dates are not yet available until we know when the supplier will engage. Because of this the project will be Amber with regards to time.
Next Steps
- Rearrange meeting with vendor to get agreements on design, agents and vendor access
- Test servers to be set up
- OCS upgraded on Test
Commentary: Project is AMBER.
Description: A meeting was arranged during PM leave for 13 Se 24 for vendor to discuss and agree server design and agent service names with Dev Services and Production. A vendor access method was also to be agreed with Production. The meeting did not happen as vendor could not make it.
Impact: Impacts the date for the Test server to be completed as we cannot move forward without vendor input
Plan: Vendor has been asked for dates as to when he can make a meeting. Timelines will be extended
Milestones
Milestone |
Due Date |
Creation of TEST and LIVE Rocky servers |
6 Sep 2024 |
TEST environment OCS upgrade completed |
30 Sep 2024 |
LIVE environment OCS upgrade completed |
14 Oct 2024 |
Post deployment support |
25 Oct 2024 |
Close |
31 Oct 2024 |
- Approved budget
- 45.0 days
- Activity this month
- 3.0 days
- Activity this year
- 8.0 days
- Activity to date
- 13.0 days
- Estimate to complete current year
- 32.0 days
- Estimate to complete future years
- 0.0 days