Report for October 2024
- Report Date
- October 2024
Achievements this period
- Finally managed to meet with supplier and an agreement on the build was reached along with new dates for the project agreed
- Servers have now been ordered - 1-2wk lead time so expected at the beginning of November
- Originally were expecting to have to build
- 2 x Test MariaDB (mariadb-ocs-kb1test & mariadb-ocs-at1test)
- 1 x Test App Server (ocs-app-test)
- 2X Live MariaDB (mariadb-ocs-kb1live & mariadb-ocs-at1live)
- 1 x Live App Server (ocs-app-live)
- But DevTech have since discussed with the Supplier and are now planning to use Docker containers and this has reduced the servers down to two
- ocsinventory-test
- ocsinventory-live
Issues
- Due to supplier being unable to attend the initial meetings the build of the servers was delayed – but they have now been ordered
- Revised milestones were therefore agreed and submitted to AppsReview
Next Steps
- Completion of server build
- Supplier to update OCS on Test
- CAHSS to test the TEST environment
Commentary: Project is GREEN
Milestones
Milestone |
Due Date |
Creation of TEST and LIVE Rocky servers |
13-Nov-2024 |
TEST environment OCS upgrade completed |
22-Nov-2024 |
LIVE environment OCS upgrade completed |
14-Jan-2025 |
Post Deployment support and DSOR |
28-Jan-2025 |
Close |
31-Jan-2025 |
- Approved budget
- 45.0 days
- Activity this month
- 6.0 days
- Activity this year
- 14.0 days
- Activity to date
- 19.0 days
- Estimate to complete current year
- 24.0 days
- Estimate to complete future years
- 0.0 days