Impact

Priority and Funding

The bussiness would like the system to be avaialable as close to the new symester as possible. However Funding is still be secured.

3 point Estimate 

HSS047_estimates_v1.1.xlsx

 

The Project have rationolised this estimate and have submitted the following breakdown by email as the 3 point estimate was not sufficient for the bussiness to commucate the breakdown as part of the funding action

 

Total Estimated Project Cost: £12,020  

This total cost comprises the following components:  

 

1. Labor Costs:  

- £10, 270  

- Based on a project of 26  days effort  

- Calculated using a day rate of £395  

 

2. Infrastructure Costs (Annual):  

- £1,750  

3.  Detailed Explanation of Costs:    

Labor Costs:  

Our project timeline estimate is 26 days total effort, covering all phases from planning through to initial production support. Using our standard blended day rate of £395, this amounts to £10,270  

 

This includes time for:  

- Project management  

- Infrastructure design  

- REDCap license procurement support  

- Building and configuring REDCap infrastructure  

- Integration and system testing  

- Deployment and validation  

- Documentation and sign-off  

- Initial production support for 1 year  

 

Infrastructure Costs:  

The annual infrastructure estimate of £1,749 covers both test and live environments and includes storage and backup costs  

 

Key Considerations:  

- The project is designed to support 500-1000 external athlete participants, with potential for future expansion to all universities.  

- We've factored in requirements for data privacy and security, including separate database servers .  

- The estimate includes initial production support for 1 year, but a long-term support strategy and funding will need to be addressed for beyond September 2024.  

- We've allocated time for determining data isolation requirements and URL finalization.  

 

 

Impact and Dependencies

The successful implementation of REDCap will significantly enhance the University's research capabilities and data management processes. It will provide a secure, efficient platform for data collection and analysis, potentially improving collaboration within the institution and with external partners. 

 

Lessons learned from previous projects

 

 

Project Risks

 

Project Info

Project
REDCap Installation Project
Code
HSS047
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Kait Simpson
Current Stage
Plan
Status
In Progress
Start Date
09-Jul-2024
Planning Date
20-Dec-2024
Delivery Date
02-Aug-2024
Close Date
09-Aug-2024
Overall Priority
Normal

Documentation

Plan