Organisation

Work/Task Breakdown

11. Work Task Breakdown 

 

1. Project Initiation 

   - Finalize project brief 

   - Obtain necessary approvals 

   - Assemble project team 

- Analysis 

2. VM Setup 

   - Coordinate with IT infrastructure team 

   - Prepare VM according to REDCap requirements 

3. REDCap Installation 

   - Install required dependencies  

   - Install REDCap software 

   - Perform initial configuration 

4. Testing 

   - Conduct system tests 

   - User acceptance testing 

5. Documentation 

   - Create New TAD 

-Document installation maintenance process 

7. Go-Live Preparation 

   - Final system checks 

   - Prepare support processes 

8. Project Closure 

   - Conduct project review 

   - Document lessons learned 

 

Resources, Skills and Costs

Project Team 

  • Peter Jackson Technical lead 
  • Andrew Thomson Dev Tech  
  • Apps Management to be engaged – Seetha S 
  • Tech Man  - Chris 

 

Project Governance

 

 

Project Stakeholders

(Please copy and paste from Stakeholder List)

  • Project Sponsor: Kait Simpson 
  • Project Manager: Joe Cowan 
  • Programme Manager: Muriel Mewissen 
  • Portfolio Manager: Muriel Mewissen 
  • Key Stakeholders: Mark Ritchie, Mark Lang, Suran Perera, Adam Wadee 

Project Estimations

(Please attach/link from Estimation Log)

 

Project Info

Project
REDCap Installation Project
Code
HSS047
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Kait Simpson
Current Stage
Plan
Status
In Progress
Start Date
09-Jul-2024
Planning Date
20-Dec-2024
Delivery Date
02-Aug-2024
Close Date
09-Aug-2024
Overall Priority
Normal

Documentation

Plan