Report for October 2024
- Report Date
- October 2024
Achievements in last period
- Initiation approved at Apps Review
- Project Brief completed and noted at Apps Review 24/10/24
- Revised estimate at planning issue log 1 approved at Apps Review 24/10/24
- Analysis has started
Issues
- New dates agreed at planning to account for delay in initiation submission
|
was |
now |
Delivery (Analysis) |
15/11/2024 |
13/12/2024 |
Close |
29/11/2024 |
22/12/2024 |
- A meeting is taking place 5 November with sponsor to discuss project scope following first meeting with business lead and SME. Expectation was that the project would be doing analysis for CRM not just file store
Next Steps
- Scope confirmed
- Analysis ongoing
Milestones
Milestone |
Due Date |
Delivery (Analysis) |
13/12/2024 |
Close |
22/12/2024 |
- Approved budget
- 36.0 days
- Activity this month
- 5.0 days
- Activity this year
- 5.0 days
- Activity to date
- 5.0 days
- Estimate to complete current year
- 32.0 days
- Estimate to complete future years
- 0.0 days