Report for August 2021

Report Date
August 2021
Project withdrawn - ITI Director approval
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Staff RDP Mitigation
Code
IDR304
Programme
ITI - Divisional and Directorate (IDR)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Anthony Weir
Current Stage
Initiate
Status
Withdrawn
Project Classification
Transform
Start Date
31-Aug-2021
Planning Date
31-Aug-2021
Delivery Date
31-Aug-2021
Close Date
31-Aug-2021
Overall Priority
Highest
Category
Discretionary

Documentation

Not available.