Report for August 2022

Report Date
August 2022
Summary

ITT published, strategy and plan in place.

 

Achievements in Last Period
  • complete project brief and planned milestones - achieved

  • complete strategy document - achieved

  • complete ITT - achieved

  • publish to procurement website - achieved

  • bidders conference  - achieved

 

Issues/Risks RED 
  • no red risks

 

Next Steps

  • clarifications

  • receive responses

  • evaluation

  •  

 

Future Milestones
Planning 05-Aug-2022
ITT 19-Aug-2022
Responses 09-Sep-2022
Evaluation 23-Sep-2022
Award 05-Oct-2022
New License  11-Nov-2022
Closure 18-Nov-2022

 

 

 

 

 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Microsoft Software Licensing Agreement Renewal
Code
IDR402
Programme
ITI - Divisional and Directorate (IDR)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-May-2022
Planning Date
12-Aug-2022
Delivery Date
30-Nov-2022
Close Date
20-Dec-2022
Overall Priority
Normal
Category
Compliance

Documentation