Report for August 2022
- Report Date
- August 2022
Summary
ITT published, strategy and plan in place.
Achievements in Last Period
-
complete project brief and planned milestones - achieved
-
complete strategy document - achieved
-
complete ITT - achieved
-
publish to procurement website - achieved
-
bidders conference - achieved
Issues/Risks RED
- no red risks
Next Steps
-
clarifications
-
receive responses
-
evaluation
-
Future Milestones
Planning | 05-Aug-2022 |
ITT | 19-Aug-2022 |
Responses | 09-Sep-2022 |
Evaluation | 23-Sep-2022 |
Award | 05-Oct-2022 |
New License | 11-Nov-2022 |
Closure | 18-Nov-2022 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days