Report for November 2024

Report Date
November 2024

Achievements this Period

  • Schedule of switch updates  progressed

Risks and Issues

  • Source of recurrent issues may not be identified
  • Delay to Delivery and Closure Milestones

Next Steps

  • Complete network changes
  • Review progress and agree if any additional steps or tests are needed.

 

Milestones

 

Deliver    24- Feb-2025

Close    31-Mar-2025

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Significant
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
Work to upgrade fibre between AT and KB not main priority so will be completed after New Year
Activity
Approved budget
40.0 days
Activity this month
0.0 days
Activity this year
1.0 day
Activity to date
1.0 day
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Infrastructure Resilience Improvements
Code
IDR602
Programme
ITI - Divisional and Directorate (IDR)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Anthony Weir
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
15-Jan-2024
Planning Date
28-Jun-2024
Delivery Date
24-Feb-2025
Close Date
31-Mar-2025
Overall Priority
Highest
Category
Discretionary

Documentation

Not available.