IBM Software Audit Return 24-25

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2024 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
IBM Software Audit Return 24-25
Code
IDR701
Programme
ITI - Divisional and Directorate (IDR)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Anthony Weir
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
08-Nov-2024
Planning Date
16-Dec-2024
Delivery Date
17-Jan-2025
Close Date
31-Jan-2025
Overall Priority
Normal
Category
Compliance

Documentation

Not available.

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.