Report for June 2015
- Report Date
- June 2015
Achievements this Period
- Presentation on PMP arranged for Dev Tech/Tech Man colleagues
- 'Priority 2' servers (Windows) removed from UoE network
- Decommissions of other servers and 15-16 decommissions planned
- Presentation to Project Services about the work of INF105
Issues
- None reported
Next Steps
- Password Manager deployment to be completed
- Final plans for Windows servers to be prepared
Milestones
24-Jul-2015 | Windows decommissioning (14-15) completed | Build |
24-Jul-2015 | Password Manager work completed | Build |
02-Nov-2015 | Unix decommissioning (15-16) completed | Build |
16-Nov-2015 | RedHat decommissioning (15-16) completed | Build |
30-Nov-2015 | Recommendations and procedures signed off | Deliver |
07-Dec-2015 | Windows decommissioning (15-16) completed | Build |
17-Dec-2015 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 11.9 days
- Activity this year
- 145.6 days
- Activity to date
- 145.6 days
- Estimate to complete current year
- 8.8 days
- Estimate to complete future years
- 100.0 days