Report for July 2015
- Report Date
- July 2015
Achievements this Period
- Password Manager deployment continued
- Removal of more Windows servers
- Removal of various Solaris boxes and databases
Issues
- None reported
Next Steps
- Plans for 15-16 migrations to be started
- PMP deployment to be completed
Milestones
27-Aug-2015 | Password Manager work completed | Build |
02-Nov-2015 | Unix decommissioning (15-16) completed | Build |
16-Nov-2015 | RedHat decommissioning (15-16) completed | Build |
30-Nov-2015 | Recommendations and procedures signed off | Deliver |
07-Dec-2015 | Windows decommissioning (15-16) completed | Build |
17-Dec-2015 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 5.5 days
- Activity this year
- 150.9 days
- Activity to date
- 150.9 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 102.0 days