Report for July 2015

Report Date
July 2015

Achievements this Period

  • Password Manager deployment continued
  • Removal of more Windows servers 
  • Removal of various Solaris boxes and databases

Issues

  • None reported 

Next Steps

  • Plans for 15-16 migrations to be started
  • PMP deployment to be completed

Milestones

27-Aug-2015Password Manager work completedBuild
02-Nov-2015Unix decommissioning (15-16) completedBuild
16-Nov-2015RedHat decommissioning (15-16) completedBuild
30-Nov-2015Recommendations and procedures signed offDeliver
07-Dec-2015Windows decommissioning (15-16) completedBuild
17-Dec-2015ClosureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
5.5 days
Activity this year
150.9 days
Activity to date
150.9 days
Estimate to complete current year
0.0 days
Estimate to complete future years
102.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance