Report for August 2015

Report Date
August 2015

 

Achievements this Period

  • Continuing work on Password Manager - now almost complete
  • Clarified position round Boombox & media servers
  • Handover meetings with new Project Sponsor

Issues

  • Uncertainty for some staff with regards to what applications need to be migrated
  • Corresponding lack of detail on what is on CF servers
  • Need to update later milestones in line with migration projects in other programmes

Next Steps

  • Reassure colleagues on details of CF applications
  • Establish details of what is on servers to be decommissioned & communicate again with service owners
  • Add details of server contents to Wiki pages

 

Milestones

02-Nov-2015Unix decommissioning (15-16) completedBuild
16-Nov-2015RedHat decommissioning (15-16) completedBuild
30-Nov-2015Recommendations and procedures signed offDeliver
07-Dec-2015Windows decommissioning (15-16) completedBuild
17-Dec-2015ClosureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
14.0 days
Activity this year
14.0 days
Activity to date
164.8 days
Estimate to complete current year
88.8 days
Estimate to complete future years
0.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance