Report for September 2015
- Report Date
- September 2015
Achievements this Period
- Clarification round CF applications to be migrated - checked with Programme Managers
- Work on Password Manager now almost complete
Issues
- Uncertainty for some staff with regards to what applications need to be migrated
- Need to update later milestones in line with migration projects in other programmes
Next Steps
- Sign off deployment of Password Manager
- Update milestones and risks round CF migrations
Milestones
02-Nov-2015 | Unix decommissioning (15-16) completed | Build |
16-Nov-2015 | RedHat decommissioning (15-16) completed | Build |
30-Nov-2015 | Recommendations and procedures signed off | Deliver |
07-Dec-2015 | Windows decommissioning (15-16) completed | Build |
17-Dec-2015 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 10.5 days
- Activity this year
- 24.5 days
- Activity to date
- 175.4 days
- Estimate to complete current year
- 79.5 days
- Estimate to complete future years
- 0.0 days