Report for October 2015

Report Date
October 2015

Achievements this Period

  • Some work on Password Manager 
  • Clarification on CF applications & EOL for annual planning

Issues

  • Need to update later milestones in line with migration projects in other programmes

Next Steps

  • Sign off deployment of Password Manager
  • Update milestones and risks round CF migrations

 

Milestones

16-Nov-2015RedHat decommissioning (15-16) completedBuild
30-Nov-2015Recommendations and procedures signed offDeliver
07-Dec-2015Windows decommissioning (15-16) completedBuild
17-Dec-2015ClosureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
4.3 days
Activity this year
31.3 days
Activity to date
183.2 days
Estimate to complete current year
70.3 days
Estimate to complete future years
0.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance