Report for November 2015
- Report Date
- November 2015
Achievements this Period
- Clarification on CF applications & EOL for annual planning
- Updated milestones and risks round CF migrations
Issues
- Still some information required from other programmes on planned migrations
Next Steps
- Continue to monitor planned migrations
- Some small migrations to be carried out - e.g. DRPS; Law website.
Project status is RED because of the changes to all outstanding milestones.
Milestones
29-Jan-2016 | Recommendations and procedures signed off | Deliver |
30-Jun-2016 | Windows decommissioning (15-16) completed | Deliver |
30-Jun-2016 | RedHat decommissioning (15-16) completed | Deliver |
30-Jun-2016 | Solaris decommissioning (15-16) completed | Deliver |
14-Jul-2016 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 5.5 days
- Activity this year
- 37.0 days
- Activity to date
- 189.5 days
- Estimate to complete current year
- 63.5 days
- Estimate to complete future years
- 0.0 days