Report for December 2015

Report Date
December 2015

Achievements this Period

  • Clarification on CF applications & EOL for annual planning
  • Updated milestones and risks round CF migrations

Issues

  • Still some information required from other programmes on planned migrations

Next Steps

  • Continue to monitor planned migrations
  • Some small migrations to be carried out - e.g. DRPS; Law website.

 

Milestones

29-Jan-2016Recommendations and procedures signed offDeliver
30-Jun-2016Windows decommissioning (15-16) completedDeliver
30-Jun-2016RedHat decommissioning (15-16) completedDeliver
30-Jun-2016Solaris decommissioning (15-16) completedDeliver
14-Jul-2016ClosureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
2.0 days
Activity this year
39.7 days
Activity to date
191.7 days
Estimate to complete current year
61.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance