Report for January 2016

Report Date
January 2016

Achievements this Period

  • Analysis for DRPS migration carried out by Development Services
  • 'Calum MacLean' database migrated from Glamis
  • Report prepared by project sponsor and PM

Issues

  • Some concerns around migrations - being monitored with project sponsor.

Next Steps

  • Continue to monitor planned migrations
  • Some small migrations to be completed - e.g. DRPS; Law website.

 

Milestones

30-Jun-2016Windows decommissioning (15-16) completedDeliver
30-Jun-2016RedHat decommissioning (15-16) completedDeliver
30-Jun-2016Solaris decommissioning (15-16) completedDeliver
14-Jul-2016ClosureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
7.8 days
Activity this year
47.3 days
Activity to date
199.0 days
Estimate to complete current year
54.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance