Report for January 2016
- Report Date
- January 2016
Achievements this Period
- Analysis for DRPS migration carried out by Development Services
- 'Calum MacLean' database migrated from Glamis
- Report prepared by project sponsor and PM
Issues
- Some concerns around migrations - being monitored with project sponsor.
Next Steps
- Continue to monitor planned migrations
- Some small migrations to be completed - e.g. DRPS; Law website.
Milestones
30-Jun-2016 | Windows decommissioning (15-16) completed | Deliver |
30-Jun-2016 | RedHat decommissioning (15-16) completed | Deliver |
30-Jun-2016 | Solaris decommissioning (15-16) completed | Deliver |
14-Jul-2016 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 7.8 days
- Activity this year
- 47.3 days
- Activity to date
- 199.0 days
- Estimate to complete current year
- 54.0 days
- Estimate to complete future years
- 0.0 days