Report for February 2016
- Report Date
- February 2016
Achievements this Period
- Further monitoring of CF migrations - all now planned or under way
- Related wiki pages and reports updated
- School of Law website migrated to new hosting service
Issues
- None reported
Next Steps
- Continue to monitor planned migrations
- DRPS migration to be completed
Milestones
30-Jun-2016 | Windows decommissioning (15-16) completed | Deliver |
30-Jun-2016 | RedHat decommissioning (15-16) completed | Deliver |
30-Jun-2016 | Solaris decommissioning (15-16) completed | Deliver |
14-Jul-2016 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 8.0 days
- Activity this year
- 56.5 days
- Activity to date
- 208.5 days
- Estimate to complete current year
- 44.5 days
- Estimate to complete future years
- 0.0 days