Report for March 2016

Report Date
March 2016

Achievements this Period

  • Further monitoring of CF migrations - all now planned or under way
  • Related wiki pages and reports updated
  • Agreement on short-term move for PURE

Issues

  • None reported

Next Steps

  • Continue to monitor planned migrations
  • DRPS migration to be completed

 

Milestones

30-Jun-2016Windows decommissioning (15-16) completedDeliver
30-Jun-2016RedHat decommissioning (15-16) completedDeliver
30-Jun-2016Solaris decommissioning (15-16) completedDeliver
14-Jul-2016ClosureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
3.5 days
Activity this year
62.3 days
Activity to date
214.2 days
Estimate to complete current year
38.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance