Report for October 2014
- Report Date
- October 2014
Achievements this Period
- Project brief prepared for submission to WIS
- Further meetings with stakeholders to establish parameters of project
Issues
- Planning sign-off moved because of sickness absence and leave (PM)
Next Steps
- Project brief to be submitted to WIS
- Work to commence on cataloguing obsolete elements in infrastructure
Milestones
07-Nov-2014 | End of Planning | Plan |
27-May-2016 | Delivery | Deliver |
01-Jul-2016 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 2.9 days
- Activity this year
- 7.6 days
- Activity to date
- 7.6 days
- Estimate to complete current year
- 144.5 days
- Estimate to complete future years
- 101.6 days