Report for April 2016
- Report Date
- April 2016
Achievements this Period
- Further monitoring of CF migrations - some completed; all now planned or under way
- Related wiki pages and reports updated
Issues
- None reported
Next Steps
- Continue to monitor planned migrations
- DRPS migration to be completed
- Some Windows servers to be migrated by Technology Management team
Milestones
30-Jun-2016 | Windows decommissioning (15-16) completed | Deliver |
30-Jun-2016 | RedHat decommissioning (15-16) completed | Deliver |
30-Jun-2016 | Solaris decommissioning (15-16) completed | Deliver |
14-Jul-2016 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 5.8 days
- Activity this year
- 69.5 days
- Activity to date
- 221.4 days
- Estimate to complete current year
- 32.2 days
- Estimate to complete future years
- 0.0 days