Report for May 2016
- Report Date
- May 2016
Achievements this Period
- Further monitoring of CF migrations - most completed; all now planned or under way
- Related wiki pages and reports updated
Issues
- None reported
Next Steps
- Continue to monitor final round of planned migrations
- Some applications to be migrated by Technology Management team
Milestones
30-Jun-2016 | Windows decommissioning (15-16) completed | Deliver |
30-Jun-2016 | RedHat decommissioning (15-16) completed | Deliver |
30-Jun-2016 | Solaris decommissioning (15-16) completed | Deliver |
14-Jul-2016 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 15.9 days
- Activity this year
- 85.4 days
- Activity to date
- 237.3 days
- Estimate to complete current year
- 15.9 days
- Estimate to complete future years
- 0.0 days