Report for June 2016
- Report Date
- June 2016
Achievements this Period
- Further monitoring of CF migrations - all now completed
- Related wiki pages and reports updated
- All LSA migrations now effected except one (HR - planned for early July)
- Red Hat & Solaris machines now availble for switching off
Issues
- Technology Management time limited for work on some migrations
Next Steps
- Final migrations to be completed
- Project closure to be drafted and circulated
- Project to be closed
Milestones
30-Jun-2016 | Windows decommissioning (15-16) completed | Deliver |
30-Jun-2016 | RedHat decommissioning (15-16) completed | Deliver |
30-Jun-2016 | Solaris decommissioning (15-16) completed | Deliver |
28-Jul-2016 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 12.4 days
- Activity this year
- 97.1 days
- Activity to date
- 248.9 days
- Estimate to complete current year
- 2.5 days
- Estimate to complete future years
- 0.0 days